Pentagon tells a court 400 onshore wind projects await review, handled by eight federal staff

The US Department of Defense has a queue of around 400 onshore wind projects waiting for its approval and does not have enough staff to work through it, according to a filing reported by Utility Dive on 12 November. The statement came from Dale Marks, assistant secretary of defense for energy, installations and environment, in a 3 November filing with the US District Court for the District of Oregon.

The filing is part of a lawsuit brought by a coalition of clean energy trade groups, developers and states. Their complaint, filed on 31 May, alleges that the department stopped carrying out its statutory duty to assess wind projects' effects on military readiness and that the process stalled after Marks was confirmed. It asks the court to vacate the department's review freeze and to order action by set dates.

In the 3 November filing, the department says it is complying with an August court injunction that stayed what it calls a temporary pause, and that it has returned to reviewing permits. It says the office responsible, the Military Aviation and Installation Assurance Siting Clearinghouse, has moved from a pause on processing to active assessment of projects. It opposed a motion by the plaintiffs to enforce the stay.

The American Clean Power Association disputes that. In a declaration dated 20 October, its vice president of policy and regulatory affairs, Tom Vinson, said the department had not resumed review and that any administrative activity had not produced substantive movement through mitigation review. He cited a project whose turbine delivery has been pushed back: equipment delivered after 31 December 2027 will not qualify for the Advanced Manufacturing Credit, which the developer estimates at about $200,000 per turbine, roughly $24 million for the project.

Marks wrote that none of the review teams is sized for the influx of applications of recent years, at a time of pressure on staff, funding and contractor support. Contractors cannot carry out inherently governmental functions, so action on the roughly 400 projects rests solely with eight federal employees. In an average year the department would sign 13 mitigation agreements; recently the number has been around 30.

The plaintiffs' reply is due on 17 November.

Pentagon tells a court 400 onshore wind projects await review, handled by eight federal staff
Pentagon tells a court 400 onshore wind projects await review, handled by eight federal staff — Grid Brief

Why it matters

The department's own numbers set the pace. By simple division, even at the recent rate of about 30 mitigation agreements a year a queue of 400 projects would take more than a decade, while developers face a tax credit deadline at the end of 2027.