NESO sends GC0168 to Ofgem: EMT models from plant built before September 2022

Great Britain's system operator NESO submitted the final modification report for Grid Code change GC0168 to the regulator Ofgem on 8 October. The change would let NESO require electromagnetic transient (EMT) models from users whose plant was completed before 1 September 2022 — the fleet connected before such models were routinely demanded.

Why NESO wants them. The report's reasoning is the shift from large synchronous machines to many smaller electronic power converters — wind, solar, batteries, HVDC — whose power electronics interact with the transmission system differently. NESO lists the problems it needs to study: system oscillations, inverter instability, low fault levels and transient overvoltage. Slower RMS models do not capture these fast interactions; EMT models do, and without them for older plant the studies have gaps.

Two versions on Ofgem's desk.

  • The original proposal: legacy users provide EMT models on NESO's request, under a new Electrical Standard (Annex 08 of the report) that sets the model requirements and the process for retrospective submission.
  • WAGCM1, the workgroup alternative: the same obligation, but its effective date for pre-September-2022 plant is deferred until a cost-recovery mechanism exists in the CUSC, the charging code. Two CUSC changes, CMP456 and CMP466, have been raised for that.
NESO sends GC0168 to Ofgem: EMT models from plant built before September 2022
NESO sends GC0168 to Ofgem: EMT models from plant built before September 2022 — Grid Brief

The workgroup backed the alternative by majority and did not back the original; the Grid Code Review Panel also recommended WAGCM1 by majority. The consultation drew five non-confidential and one confidential response.

The cost argument. Workgroup members agreed that older plant should be compensated but said the bill is hard to quantify: it depends on unit size, age, type and whether the manufacturer still supports the equipment — for some legacy converters, building a validated EMT model means reverse-engineering controls the vendor no longer documents. NESO's representative noted cost recovery would apply only to historical sites; new connections are already expected to supply models.

What happens next. Implementation is set for 10 business days after Ofgem's decision. A parallel change for transmission owners (STC CM097) and a new code procedure (PM0147) run alongside. If Ofgem picks the alternative, the practical start depends on the CUSC cost-recovery changes — so owners of pre-2022 wind, solar and battery sites should follow CMP456 as closely as GC0168 itself.

Source: NESO, "GC0168 Final Modification Report", 8 October 2026 — https://www.neso.energy/gc0168-final-modification-report

Primary source
NESO (UK system operator)
https://www.neso.energy/gc0168-final-modification-report