Delhi cut its grid losses from over 50% to about 5% in 24 years
Delhi's electricity distribution grid lost more than half of the power it carried in 2002 and now loses 5 to 6%, on a par with France and Belgium, according to an account published by IEEE Spectrum and written by a professor of electrical engineering at Jamia Millia Islamia in the city. Over the same period the city's grid reliability index rose from around 70% to above 99.9%.
The starting point, as the article describes it, was a distribution system nearly a century old, with worn-out lines, transformers and breakers, rampant theft and weak billing. Reactive loads pushed up current, which raised losses and dragged voltage down, and appliances then drew even more current. Meters were old and easily tampered with, bills were delivered by hand from paper records, payment meant queueing at offices with short hours, and there was no rule allowing a utility to cut off a customer who did not pay.
The turn came in 2002, when the Delhi Vidyut Board was broken up and two private companies, BSES and Tata Power, took over distribution. Tata Power inherited combined losses of 53.5% in the north; BSES faced 51.5% in South Delhi and 63.1% in East Delhi. The national Electricity Act of 2003 then unbundled generation, transmission and distribution, opened the sector to private operators and created mechanisms for prosecuting electricity theft. The utilities installed capacitor banks to supply reactive power locally, replaced overhead lines with underground cable in places and rolled out better meters. Tata Power's own losses fell from 53.1% in 2002 to 6.3% in 2023.
The city of about 23 million people reached a record peak demand of 8,748 MW this year and buys 76% of its power from outside.

What it means
The article's point is that most of the fix was not new generation but plain distribution engineering combined with accountability: measuring what flows, billing what is used and compensating reactive power where it is consumed. The author names Albania, Argentina, Bangladesh, Kenya, Pakistan and others as places where losses today look like Delhi's did.