Lacour refers West Arthur, 92 turbines with a 500 MW/4,000 MWh battery, under the EPBC Act
Lacour Energy, a developer based in Western Australia, has asked the federal government to assess its West Arthur Wind Farm under the Environment Protection and Biodiversity Conservation (EPBC) Act. The referral was lodged through its project company West Arthur Energy, Energy-Storage.news reported on 13 November. The project would pair up to 92 wind turbines with a battery energy storage system of up to 500 MW/4,000 MWh, an eight-hour duration.
The site lies about 3 km south of Darkan and 40 km east of Collie in the Shire of West Arthur. A referral asks the federal government to decide whether a project could significantly affect matters of national environmental significance, such as threatened species, and therefore needs approval as a controlled action.
Each turbine would be rated 6-8 MW with a tip height of up to 253 m. The referral does not give a total wind capacity; 92 turbines at 8 MW would make 736 MW, while the federal government lists West Arthur as a 500 MW wind farm on the National Renewable Energy Priority List, which the project joined in June 2026.
The project would connect to the South West Interconnected System (SWIS), Western Australia's main grid, which is outside the National Electricity Market. The connection would run through the proposed Clean Energy Link-East transmission line to a proposed Cordering substation operated by Western Power, which expects construction of the line to finish by the end of 2029.
The referral gives an estimated start date of 1 July 2027, two to three years of construction and an operating life of about 60 years. The indicative disturbance footprint is about 565 hectares of a 10,996.76-hectare project area, including 6.28 hectares of native vegetation and fauna habitat, with about 1,738 hectares of mapped native vegetation set aside. The developer assessed significant impacts on threatened communities, flora and critical habitat as unlikely. It also referred the project to the state's Environmental Protection Authority on 15 October and lodged a development application with the shire in September.
At eight hours, the battery would have a longer duration than the largest systems already on the SWIS: Synergy's 500 MW/2,400 MWh Collie Battery, completed in February, and Neoen's 560 MW/2,240 MWh Collie BESS nearby. Utility-scale batteries supplied a record 37.2% of peak demand on the WA grid on 9 May, according to Energy Policy WA.

Why it matters
The referral shows the duration of storage in Western Australia moving from four or five hours towards eight on an isolated grid that cannot import from the eastern states. The timeline also shows the bottleneck: the battery depends on a transmission line due at the end of 2029 and on a federal approval process that, in another recent case, took more than four years.