ju:niz picks Envision for Smareg 13, a 442 MWh four-hour grid-forming battery in Bavaria
German battery developer ju:niz Energy has chosen Envision Energy to supply a 442 MWh storage system in Bavaria, Energy-Storage.news reports. The project, Smareg 13, also called Vöhringen II, will sit next to ju:niz's operating Smareg 12 system in Vöhringen. It will have a four-hour duration and grid-forming capability.
The split of roles is standard for such deals. ju:niz, which is owned by private equity firm EQT, handles development, financing and construction and will operate the plant over the long term. Envision supplies its Gen 8 battery platform and runs project delivery. The companies did not disclose the power rating in MW, the cost, the financing or the expected start of operation.
It is the third project between the two, bringing their combined volume to nearly 600 MWh. The first two, announced at Intersolar Europe this year, are the 88.4 MWh S10 project in Baindt and the 52.2 MWh S15 project in Schöningen, Envision's first Gen 8 sites in Germany. Envision's Henry Peng noted that the third deal was agreed before the first two had finished delivery.
Noise was a site issue. According to the release, the low-noise design of Gen 8 addressed one of the key challenges at Smareg 13, an acoustically sensitive location. When Envision launched the platform in October 2025, it quoted 55 to 58 dB for its 10-foot DC blocks, which use lithium-ion cells of 750 Ah and above in configurations from 6 MWh to more than 12 MWh. The release did not say whether Envision also supplies the power conversion equipment, the inverters on which grid-forming behaviour depends.
The revenue case has a new element. German transmission system operators began procuring inertia, known as Momentanreserve, in January 2026 under contracts of two to ten years that pay a fixed price per unit of registered capacity, and grid-forming batteries can take part.
Context from the same report: Germany has around 24 GWh of storage connected, of which large systems above 1 MWh account for only about 3.5 GWh, and the four TSOs have received nearly 700 connection requests totalling 250 GW.

Why it matters
Grid-forming capability turns a battery from an energy trader into a provider of system stability, and the new inertia market gives that a price in Germany.