IEEFA: Australia's remaining battery gap to 2030 could be in construction within 18 months

Australia committed a record 2.4 GW of renewable energy projects to construction in the third quarter of 2026, and the battery projects committed in the same quarter covered 13 percent of the new storage capacity the country needs by 2030, according to the latest Australian Renewable Energy Scorecard, reported by Energy-Storage.news on 20 November. The scorecard is published every quarter by the Institute for Energy Economics and Financial Analysis (IEEFA) and the consultancy Green Energy Markets.

The 2.4 GW is 20 percent above the previous record from the first quarter of 2022, after two weak quarters this year; wind accounted for 1.5 GW. For utility-scale batteries the report says that at the current rate the remaining gap to 2030 could be in construction in less than a year and a half. Its charts put the battery capacity needed by 2030 at about 105 GWh, against roughly 30 GWh under construction and more than 200 GWh in development, not counting early-stage proposals; New South Wales has the largest requirement, at about 45 GWh.

Contracts remain the obstacle for wind and solar. Only 6 percent of fully approved projects also have a contract, and of 25.5 GW of wind and solar awarded federal or New South Wales underwriting just 4.6 GW, or 18 percent, has reached construction or operation. Officials disclosed in October that 27 of the 109 projects awarded Capacity Investment Scheme agreements will not proceed with them; IEEFA has not adjusted its charts because the projects have not been named. Behind the meter, home battery installations fell 44 percent in the quarter after a record second quarter, which the scorecard links to the scaling back of the Cheaper Home Batteries Program rebate in May.

IEEFA: Australia's remaining battery gap to 2030 could be in construction within 18 months
IEEFA: Australia's remaining battery gap to 2030 could be in construction within 18 months — Grid Brief

Why it matters

The figures split Australia's transition in two: grid batteries are on course to close their 2030 gap early, while wind and solar stall between approval and contract. The government's unnamed list of withdrawn CIS projects means the published pipeline still overstates what will be built.