EDF buys the 250 MW, four-hour Holloway battery project in New South Wales

EDF power solutions Australia has acquired the 250 MW Holloway battery energy storage project in New South Wales from developer SynCo Global, Energy-Storage.News reported on 20 November. EDF says the system will have up to four hours of storage; planning documents lodged with the NSW Department of Planning describe it as 250 MW/1,000 MWh. The price was not disclosed.

Holloway is being assessed as a State Significant Development and is at the stage of preparing its environmental impact statement. EDF says the statement will go on public exhibition in the coming months, with a final investment decision targeted for late 2027 and operations from 2029. EDF Australia chief executive James Katsikas said such projects are needed to capture surplus renewable generation and make it available when homes and businesses need it.

The project joins a cluster of batteries around Armidale, including Valent Energy's 150 MW/437 MWh system connecting to the 330 kV Armidale substation and ACEnergy's proposed 400 MW/1,760 MWh Gara project. EDF's Australian pipeline also includes pumped hydro: the Wala Wala project in the Dungowan Valley, 300-400 MW with up to 4,000 MWh, and a 75% stake in the 385 MW/3,080 MWh Lake Lyell project with EnergyAustralia. Contracted new storage in NSW stands at 30 GWh against a 42 GWh target for 2034.

EDF buys the 250 MW, four-hour Holloway battery project in New South Wales
EDF buys the 250 MW, four-hour Holloway battery project in New South Wales — Grid Brief

Why it matters

The purchase buys a place in the queue rather than a working battery: on EDF's own timetable, the first power from Holloway is due in 2029, after an investment decision planned for late 2027.