Grid Brief ENDE

AGL installs the first 100 units at its 2,000 MWh Tomago battery

AGL said on 18 November that the first 100 of more than 400 units are in place at its Tomago battery energy storage system in the Hunter region of New South Wales, according to Energy-Storage.news. The 500 MW, four-hour project, rated at 2,000 MWh, is being built in the Tomago Industrial Estate north-west of Newcastle at a cost of A$800 million (about US$538 million) and will connect to the National Electricity Market.

Concrete foundations are finished, the first of two main transformers arrived last week, and crews are laying cabling and installing inverters, with more than 200 workers on site since construction began in December 2025. AGL says the project remains on track for completion in late 2027. The state government approved planning in November 2024, when AGL put the cost at about A$1 billion, and in May 2026 awarded the project underwriting through its Long-Term Energy Service Agreement scheme.

Fluence is supplying its Gridstack Pro system, which it called its biggest deal globally when AGL took the final investment decision in July 2025, and is also building and maintaining the plant. The battery uses grid-forming inverters that can provide system strength without the synchronous machines of coal and gas plants. The units were staged at the Port of Newcastle's Mayfield terminal, the first port in the state cleared to handle grid-scale lithium-ion batteries.

AGL installs the first 100 units at its 2,000 MWh Tomago battery
AGL installs the first 100 units at its 2,000 MWh Tomago battery — Grid Brief

Why it matters

Grid-forming inverters are the point here, not only the megawatt-hours. In a region that has lost coal units, a battery that can provide system strength takes on a role the network used to get only from spinning machines.

Written by Victoria Shinder.