Romania's regulator counts 114.9 GW of renewables with grid permits, 16.2 GW fully authorised
Romania's energy regulator ANRE has published its monthly count of renewable projects larger than 1 MW, and pv magazine summarised the figures as of 1 October. On paper the pipeline is enormous: 1,625 projects hold valid grid connection permits, with a combined approved export capacity of 114.9 GW.
The numbers shrink quickly at each stage. Of those projects, 1,055, worth 63.7 GW, have also signed connection contracts. Building permits are held by 749 projects with 41 GW. Only 262 projects, representing 16.2 GW, also have ANRE's establishment authorisation, the third of the major approvals.
Month on month the picture moves slowly in the right direction. Compared with the start of September, the number of projects with valid connection permits fell by 1.1%, while the capacity of projects holding all three approvals rose by 5.28%, which suggests some projects are advancing while others drop out.
Storage is a large part of the advanced group. Of the 749 projects with both connection and building permits, 238 include storage or are standalone storage plants, with more than 15.3 GW of approved maximum export capacity; just over 4 GW of that is scheduled to start in 2026. ANRE's schedule shows 259 projects with 13.02 GW due online in 2027 and 730 projects with 40.4 GW scheduled between 2026 and 2035.
For context, pv magazine notes Romania added about 2.2 GW of solar last year and passed 8.5 GW of cumulative solar by mid-2026, which would put the 10 GW target for 2030 within reach before the end of 2027 if the pace holds.

Why it matters
A connection permit reserves grid capacity; it does not build anything. The gap between 114.9 GW permitted and 16.2 GW fully authorised is the part of the pipeline that may be holding capacity other projects could use, which is why the regulator's monthly attrition figures are worth watching.