Dogger Bank has about 150 turbines up as SSE carries out remediation work on its first phase
About 150 turbines have been installed across the three phases of the 3.6 GW Dogger Bank offshore wind farm and roughly 100 of them commissioned, offshoreWIND.biz reported on 20 November from SSE's half-year results, published on 18 November. SSE said some turbines installed in the first campaign at the 1.2 GW Dogger Bank A needed additional work to meet the required quality and reliability standards, and that this remediation is under way.
Most of Dogger Bank A's turbines have been commissioned. SSE now expects the phase's capacity to be substantially available by the end of the first quarter of 2027, with the rest coming online during final commissioning by the end of the third quarter. At Dogger Bank B, 52 of 95 turbines have been installed, at a rate SSE says is well ahead of the first phase, and most of its 1.2 GW is expected to be available in the first half of 2027. At Dogger Bank C the foundations are in place, the array cables are laid and testing is in progress; a second installation vessel, Cadeler's Wind Apex, is due to join the campaign in the third quarter of 2027.
SSE also reported on its 1.4 GW Berwick Bank B project in Scotland. It plans a final investment decision in the second half of 2027, has signed preferred supplier agreements across the project and has locked in about 60 percent of the expected debt at swap rates below 5 percent. Preparatory offshore construction could start in 2028.

Why it matters
The schedule now separates installation from availability: turbines standing at sea are not all producing yet, and the remediation at the first phase sets the date when its 1.2 GW is substantially available. The faster pace at the second phase suggests the lessons were applied as construction moved on.