Skanska completes a precast aseismic bearing demonstrator for Rolls-Royce SMR
Skanska UK has finished the demonstrator it was hired to build in January: a precast pedestal for the seismic bearings of the Rolls-Royce SMR, World Nuclear News reported on 18 November. Aseismic bearings sit beneath the nuclear island and decouple the reactor building from ground motion in an earthquake, absorbing and dissipating seismic energy so that less force reaches the structure above.
Skanska said the demonstrator, built and trialled at its Bentley Works facility in Doncaster, England, proved the approach to producing what it calls a first-of-its-kind precast bearing pedestal off site. Ruth Todd, operations and supply chain director at Rolls-Royce SMR, said testing and refining critical components before deployment reduces risk and improves predictability, and that the company's delivery programme is ramping up.
The Rolls-Royce SMR is a 470 MWe design based on a small pressurised water reactor. According to the company, 90% of the plant will be built in factory conditions, leaving mostly assembly of pre-tested modules on site. ČEZ selected it in October 2024 for up to 3 GW in the Czech Republic, with the first unit planned near Temelín, and the UK government chose it in June 2025 as its preferred technology for the country's first SMR project.

Why it matters
The demonstrator tests the construction method, not the reactor: whether a heavy, safety-relevant civil component can be made in a factory to the required tolerance. That is the part of the factory-built promise most projects have not yet shown.