NuclearSeven test rigs are running at the Chusclan site, from powder dosing to helium filling; the company's planned MOX plant in Aube would cost €1.8bn for a first line due in 2030.
NuclearA new line at its Albuquerque campus measures diameter, geometry and density, scans each surface to the micron and etches three data matrix codes; the near-term target is 70,000 inspected pebbles.
NuclearThe Rosatom-built unit achieved a sustained chain reaction on 11 October, three days after regulatory approval; power start-up is scheduled for 20 November.
NuclearSix of eight new centrifuge cascades at the National Enrichment Facility in Eunice, New Mexico, can now produce more than 500,000 SWU a year; the seventh is due later this year and the last in spring 2027.
NuclearRosatom says the VVER-1200's primary circuit held 24.5 MPa, about one and a half times operating pressure; hot tests with all four main pumps at 260°C or more must follow before fuel can be loaded.
NuclearFramatome and EDF UK renewed their long-term service agreement for Britain's only PWR through 2040, covering outages, steam generators, pumps and inspections; the release gives two different lifetime output figures.
NuclearPEJ commissioned Westinghouse to begin procuring six nuclear-island components, including the containment vessel, while the EPC contract is still being negotiated; first concrete is planned for Q4 2028.
NuclearCNNC said the unit was connected on 8 October, just over a week after first criticality; power will be raised in stages before commercial operation, which was scheduled for 2026.
NuclearThe U3O8 storage facility at Urenco's German enrichment plant is now formally in service; tails go to Pierrelatte and Capenhurst for deconversion and can come back to Gronau as stable oxide.
NuclearCNNC poured the last concrete for Zhangzhou 3's inner dome on 30 September. CGN says Zhaoyuan, a planned six-unit, 7.2 GWe plant with cooling towers instead of direct sea cooling, is at peak civil construction.