OPG says first Darlington BWRX-300 will miss its October 2030 date and CAD 7.7bn estimate
The first small modular reactor at Ontario's Darlington site will be late and over budget. Ontario Power Generation said with its third-quarter 2026 results that Unit 1 of the Darlington New Nuclear Project is no longer expected to reach commercial operation by October 2030, its previously disclosed target, or to be completed within the earlier estimate of CAD 7.7 billion, a figure that included systems and services shared by all four planned units. World Nuclear News reported the update.
OPG did not give new figures. It is carrying out a full reassessment of cost and schedule and expects to substantially complete it by mid-2027. The company attributed the slip to GE Vernova Hitachi Nuclear Energy's ongoing engineering for what it calls a first-of-a-kind SMR, which it says is affecting construction and supply chain performance. The assessment will look at design maturity and completion dates, the effect of first-of-a-kind complexity on construction and procurement assumptions, market conditions including inflation and geopolitical risk, and how well mitigation measures are working.
President and chief executive Nicolle Butcher said the company had identified risks that will affect Unit 1's schedule and budget and wanted to set a cost and schedule outlook it could stand behind. A GE Vernova Hitachi spokesperson, quoted by The Globe and Mail, said the overruns stem from several connected factors across engineering, procurement and construction, as well as inflation and geopolitical risk, rather than engineering alone.
The project is the first new nuclear build in Ontario in more than three decades. The Canadian Nuclear Safety Commission issued a construction licence for the first of four BWRX-300 units in April 2025, and the province approved a CAD 20.9 billion budget for the four-unit project the following month. Site preparation began in autumn 2022; the reactor building's basemat module was placed 35 metres below ground in April.
The BWRX-300 is a 300 MWe boiling water reactor with natural circulation and passive safety systems, based on the US-certified ESBWR design.

Why it matters
Darlington is the lead project for the BWRX-300 design. Its revised numbers, due by mid-2027, will be the first real cost and schedule data for the reactor, and other buyers of the same design will be reading them.