NRC grants permit for Dow's four-unit Xe-100 plant, first gas-cooled reactor in 60 years
The US Nuclear Regulatory Commission has issued a construction permit for the Long Mott Generating Station, four X-energy Xe-100 units at Dow's Seadrift site in Texas, World Nuclear News reported on 10 November. It is the first US construction permit for a high-temperature gas-cooled reactor in nearly 60 years. Gridbrief covered the NRC's completed safety review for the project on 3 November; the permit is the step that followed it.
The NRC lists several firsts in the decision: its first approval of a multi-module advanced reactor plant, of a pebble-bed core, of a design with online refuelling, and its first review of a gas-cooled reactor under the risk-informed Licensing Modernization Project framework. Chairman Ho Nieh said the agency met its 18-month schedule. X-energy chief executive Clay Sell said the permit arrived earlier than expected, crediting the NRC and reforms required by Congress over the past six years.
Each Xe-100 is rated at 80 MWe and 200 MWt and uses TRISO-X coated particle fuel, where each particle's coating acts as its own barrier for fission products at high temperature. According to the developers, this supports an emergency planning zone of 400 metres, against ten miles for conventional light-water reactors. The plant is meant to supply both electricity and high-temperature steam to Seadrift, replacing ageing energy and steam assets for 60 years.
The permit does not mean construction. It authorises building, not operation, which needs a separate operating licence. Dow, which develops the plant through its subsidiary Long Mott Energy under the Department of Energy's Advanced Reactor Demonstration Program, has not made a final decision. Further engineering, design work and a review by Dow's board come first; a preliminary investment decision is expected in 2027, and if the project proceeds, construction could start later this decade with start-up early next decade. Edward Stones of Dow said the company will judge the project on competitiveness, readiness and capital affordability before deciding.

Why it matters
The regulatory question for this design is now largely answered, so the remaining risk sits with Dow's investment case. The permit lets the partners order long-lead components and prepare the operating licence while that decision is pending.