Bangladesh's Rooppur 1 supplies the country's first nuclear electricity

Rooppur 1, Bangladesh's first nuclear power unit, has been connected to the national grid and supplied its first electricity, World Nuclear News reported on 17 November. The trial grid connection took place at 15:16 local time with an output of 350 MWe; each of the plant's two units has a capacity of 1,200 MWe.

Nuclear Power Plant Company Bangladesh Limited said the electricity would be supplied to the grid for about 8-10 hours while the integrated management system with turbines, generators and the grid is monitored. In the next phase the plant will be temporarily disconnected for technical tests and, after a break of about 28 hours, reconnected for about 4-6 hours. If all tests succeed, commercial supply from the first unit will begin.

The company said reconnection for trial operation awaits approval from the Bangladesh Atomic Energy Regulatory Authority, and that "following the completion of a 10-month trial operation, the first unit will begin regular commercial electricity supply at full capacity", in collaboration with Russia. World Nuclear Association director general Sama Bilbao y León called the unit "a transformative investment in the country's future".

Bangladesh's Rooppur 1 supplies the country's first nuclear electricity
Bangladesh's Rooppur 1 supplies the country's first nuclear electricity — Grid Brief

Why it matters

First electricity is a test step, not the start of commercial service: the operator itself sets out a sequence of short grid connections, a regulator's approval and a 10-month trial before the unit runs at its full 1,200 MWe.