Akkuyu 1 passes eight days of strength and leak tests on its inner containment at 0.46 MPa

Akkuyu Nuclear has completed strength and leak-tightness tests of the inner containment building at unit 1 of Turkey's first nuclear power plant, World Nuclear News reported on 13 November. The pre-launch tests lasted eight days.

During the tests the air pressure inside the containment was raised to 0.46 MPa, which corresponds to a load of about 47 tonnes on each square metre of the containment surface. The pressure was then lowered in stages, down to below atmospheric pressure, while the condition of the structure was checked, including stresses and changes in its shape and dimensions under load. Leak tightness was checked at both raised and reduced pressure.

Sergei Butckikh, chief executive of Akkuyu Nuclear JSC, said the results confirm the quality of the containment construction work and allow the project to move shortly to the next stage of pre-start-up commissioning, the cold and hot functional testing of the reactor plant.

The VVER-1200 design has two containments. The inner one protects the main reactor equipment and prevents releases to the environment; the outer reinforced concrete building is designed to protect the unit from extreme external events.

Akkuyu, in Mersin province, is being built by Rosatom with four VVER-1200 units under a build-own-operate model. The construction licence for unit 1 was issued in 2018, fuel arrived in April 2023, and the aim has been for the unit to start supplying Turkey's energy system by the end of 2026. Under the 2010 intergovernmental agreement, the first unit was to be commissioned within seven years of receiving all permits. The complete 4,800 MWe plant is expected to meet about 10% of Turkey's electricity needs.

WNN also notes Turkey's wider plans: a second plant at Sinop, talks with China on a third in Thrace, a memorandum signed on 12 November with AtkinsRéalis's Candu Energy for a feasibility study of up to six Candu reactors totalling 4.5 GW, and a goal of 5 GWe of small modular reactors by 2050.

Akkuyu 1 passes eight days of strength and leak tests on its inner containment at 0.46 MPa
Akkuyu 1 passes eight days of strength and leak tests on its inner containment at 0.46 MPa — Grid Brief

Why it matters

With about six weeks of 2026 left, unit 1 still has cold and hot functional testing ahead of it before it can supply power. The report does not give a new date, so the end-of-2026 target stands as stated, but the remaining steps are now clear.

Written by Victoria Shinder.