Grid Brief ENDE

Seven states' advocates ask PJM to delay its December capacity auction

Ratepayer advocates from seven states, including Pennsylvania, Ohio and New Jersey, asked PJM Interconnection's board in a letter on 18 November to postpone the base capacity auction for the 2029/30 delivery year, scheduled for 9 to 15 December, according to Utility Dive. They want it held only after "data center loads, both real and speculative, can be removed from the load forecast" and after a separate reliability backstop procurement for large loads. They asked for a written reply by 23 November; a delay would also need approval from the Federal Energy Regulatory Commission.

The letter builds on a 12 November report from PJM's independent market monitor, Monitoring Analytics, which warned that the forecast includes data centres that have been cancelled or are unlikely to reach projected demand, and that this could add $5 billion to $10 billion in costs for PJM's 67 million consumers. The monitor's report also put the increase in capacity costs from existing and forecast data-centre demand so far at $29.4 billion.

PJM is pushing back. A spokesman said the December auction has a price cap that limits how high prices can go, and that "postponing the auction this close to its execution could destabilize the market and increase the risk of power interruptions". PJM planned to publish the final planning parameters for the auction on 19 November, which may take cancelled or delayed data-centre projects out of the demand curve.

Seven states' advocates ask PJM to delay its December capacity auction
Seven states' advocates ask PJM to delay its December capacity auction — Grid Brief

Why it matters

A capacity auction three years ahead commits consumers to paying for demand that may not show up. The planning parameters PJM publishes before the auction are now the lever: if they remove the speculative load, the case for delay weakens; if not, the advocates' request goes to FERC.

Written by Victoria Shinder.