Exelon seeks a prompt PJM capacity auction; Invenergy wants MISO to pay HVDC lines
Two complaints filed at the Federal Energy Regulatory Commission in the first week of November challenge how the two largest US capacity markets work, Utility Dive reported on 5 November.
Exelon, whose utilities serve about 10.7 million customers in PJM, asked FERC on 3 November to order PJM to replace its auctions held three years ahead with a prompt auction run two months before the delivery year, starting with 2030/31. Under the proposal the December auction for 2029/30 would go ahead as planned and the next would follow in early 2030. Exelon argues the market no longer works properly and that a prompt auction would rest on more accurate load forecasts, resource data and accreditation, and send clearer signals for plants to enter or leave. It asked for a decision by 31 January, before PJM publishes planning parameters for a 2030/31 auction scheduled for May.
PJM said it is reviewing the complaint. It is already collecting reform ideas: more than 30 papers have been submitted and will be discussed at a workshop on 13 November, and in May it set out three paths, stabilising the current market, rationing reliability between customer classes or regions, or moving towards energy and ancillary services.
Invenergy Transmission filed on 4 November against MISO. It says MISO counts the capacity value of merchant high-voltage direct current lines when deciding how much capacity to buy, which lowers its purchases, but bars those lines from being accredited or paid. Merchant lines recover costs from negotiated rates, Invenergy notes, so without a capacity product there is nothing to sell in MISO. By one accreditation method its 5 GW, 600 kV Grain Belt Express, an 800-mile line from Kansas to Indiana costing about $11 billion, could supply more than 1,800 MW of accredited capacity.

What it means
Both cases ask who is paid for providing reliability and when. A shorter auction horizon and a new class of capacity sellers would each change prices in markets that are already under strain from load growth.