EIA expects US coal use to fall 7% in 2026 and another 5% in 2027 as 13 GW of coal retires
The electricity section of the US Energy Information Administration's November Short-Term Energy Outlook, released on 10 November, puts most of the growth in power generation on solar and most of the decline on coal.
EIA estimates that the electric power sector will generate almost 4,390 billion kilowatthours in 2026, a record and 2.7% more than in 2025, and that growth will slow to 1.2% in 2027 as milder summer weather reduces residential demand. The share of generation from utility-scale solar rises from 7% in 2025 to 8% in 2026 and nearly 10% in 2027, and wind from 11% to 12% by 2027. EIA expects 72 GW of new solar and 20 GW of new wind capacity this year and next. Natural gas stays close to 40% of generation in both years and nuclear averages 18%.
Coal falls from 17% of generation in 2025 to 15% in 2027, as 13 GW of coal capacity is scheduled to retire by the end of 2027. EIA forecasts coal consumption of 419 million short tons in 2026, 7% less than in 2025, and another 5% less in 2027. The power sector, about 90% of domestic coal use, has burned less coal than a year earlier in eight of the first ten months of 2026. EIA attributes that to more wind and solar capacity and to a 9% lower average gas price for power plants in the second and third quarters. For 2027 it expects gas prices for generators to fall 19%.
Production falls less than consumption, by 2% this year, because coal exports rise 11% from 2025. In 2027 EIA expects production to drop 4% with flat exports, which it says are supported by demand in Europe and Asia and by China's commitment to buy 10 million metric tons of US coal in both 2027 and 2028.
In the outlook's table, the average residential electricity price rises from 17.2 cents per kilowatthour in 2025 to 18.2 cents in 2026 and 18.7 cents in 2027. Solar capacity grows from 152 GW in 2025 to 223 GW in 2027, and wind from 159 GW to 179 GW.

Why it matters
The forecast attributes coal's decline to cheaper gas and new renewables, and it already counts 13 GW of scheduled retirements. Federal orders that keep individual plants available, like the one for Michigan's Campbell plant, sit outside that count.