NYISO finds a statewide shortfall of 225 MW from 2033, rising past 1,850 MW by 2036
The New York Independent System Operator said on 18 November that the state faces its first statewide resource deficiency, about 225 MW beginning in 2033 and growing to more than 1,850 MW by 2036. The finding comes from its 2026 Reliability Needs Assessment. NYISO expects 2,700 MW of new large-load demand in service by 2036 - about 1,000 MW from manufacturing and 1,700 MW from data centres - while about 5,400 MW of gas generation in the eastern part of the state is projected to be unavailable at winter peak, partly because of fuel delivery constraints, and about 4,000 MW of ageing generation is expected to retire.
The assessment also shows rising reliance on emergency operating procedures - demand response, voltage reductions, operating reserves, load curtailment and similar measures. NYISO expects to call on them on about 3.5 days next year and on 21 days by 2036. Locally, New York City is projected to be short about 400 MW in 2032, growing to about 1,850 MW by 2036, and the Lower Hudson Valley from about 130 MW to about 1,950 MW over the same period. About 4,600 MW of fossil generation will be more than 70 years old by 2036; the study treats about 2,600 MW of it as unavailable.
The operator says transmission can help with local needs but cannot resolve the statewide shortfall, which will need new generation, repowering, storage, demand reductions, flexible large loads and more transmission. Once its board approves the assessment, NYISO will request base-case updates; if needs remain, it will solicit market-based solutions and regulated backstops in its 2027-2036 Comprehensive Reliability Plan.

Why it matters
The number to watch is not only the megawatt gap but the days on emergency measures: going from 3.5 to 21 a year means tools designed for rare events become a routine part of keeping the lights on.