Grid utilisation sits at 40-60%, and non-firm transmission is the gap, Google's Norris says

Transmission owners, grid operators and policymakers already have options for adding headroom to the grid, according to panellists from utilities and technology companies at the 2026 BNEF Houston Summit on 11 November. Utility Dive's Brian Martucci reported the discussion on 13 November.

Tyler Norris, head of market innovation for energy and power at Google, put estimated grid utilisation rates at 40% to 60% and called better access to non-firm transmission service the "real whitespace". Large-load customers will contribute flexible capacity if it lets them connect sooner, he said. His example was a deal between Aligned Data Centers and Portland General Electric, under which the developer agreed to install a 31 MW/62 MWh battery for a 72 MW data centre in Hillsboro, Oregon. According to Norris, that let the project avoid a fully firmed network upgrade.

The report places these figures next to published ones. Grid Strategies, which defines load factor as average energy use divided by peak load, put the US systemwide load factor at about 60%, heading for 66% by 2030. Dominion Energy's Virginia subsidiary, answering a state legislative mandate, disclosed last month that its distribution grid runs at an average load factor of 41% with peaks just under 80% utilisation, and that the median facility utilisation of its transmission system is about 33%, while individual facilities may approach or exceed rated capacity during outages, demand peaks or large power transfers.

Jessica Hogle of NRG said the company aims for 25 GW of demand response, energy storage and virtual power plant capacity by 2035. Dave Berry of Cloverleaf Infrastructure pointed to Remedial Action Schemes, common in the Western Interconnection, which define how the grid responds to an outage; their drawback, he said, is that curtailing generation or load to protect one area can harm another. Arushi Sharma Frank, an adviser to the Utilize Coalition, expects more software-based flexibility and said new computing capacity lets utilities see grid capacity they could not see before.

Grid utilisation sits at 40-60%, and non-firm transmission is the gap, Google's Norris says
Grid utilisation sits at 40-60%, and non-firm transmission is the gap, Google's Norris says — Grid Brief

Why it matters

The utilisation numbers are averages, and the Dominion disclosure shows why they cannot be read as spare capacity: a median of 33% sits alongside facilities that reach their limits at peak. The Oregon battery is the more concrete point. It trades a firm upgrade for a commitment by the load to behave flexibly, which shifts the reliability question from the network owner to the contract.

Written by Victoria Shinder.