Eversource and National Grid use virtual power plants as a bridge to new wires
Executives of Eversource and National Grid said aggregated distributed energy resources have become a "bridge to wires" in Northeastern load pockets where demand grows faster than traditional grid infrastructure, Utility Dive reported on 18 November from a Latitude Media webinar sponsored by EnergyHub. Devices enrolled in the ConnectedSolutions and ConnectedSolutions+ programmes are increasingly used to solve location-specific distribution constraints rather than only to shave system peaks, said Steve Caldwell of National Grid.
The portfolios are large. Eversource has about 100,000 thermostats and 25,000 commercial and industrial customers enrolled across a territory that includes Greater Boston, ISO-New England's biggest load zone, according to its vice president Tilak Subrahmanian. National Grid has about 100 MW of DER load in New England and more than 350 MW in upstate New York, around 2% and 5% of regional peak. EnergyHub, which manages about 4 GW of flexible capacity, says its clients called around 3,500 load-shifting events this summer.
ConnectedSolutions+ pays higher incentives to device owners on constrained feeders. Eversource announced two pilots this year: one around three substations in Greater Boston to shift load away from peaks, and one around a single substation in southeastern Massachusetts partly to absorb excess midday solar. Subrahmanian said distributed resources do not always beat poles and wires on cost: "we have to be very specific about what problem we're trying to solve."

Why it matters
The shift is from system-wide to local: a device is worth more on an overloaded feeder than one a mile away. Both utilities present it as buying time before building, not as a replacement for building.