ENTSO-E counts what Europe's TSOs need to 2035: 34,000 km of HVDC cable, 119 converters

ENTSO-E, the association of Europe's transmission system operators, has published its Transmission Grid Investment and Supply Chain Assessment Report 2026, a ten-year view of the equipment its members plan to install. The aim, according to the association, is to give manufacturers a demand signal credible enough to justify new factories, production lines and staff.

The report covers seven asset categories from 2026 to 2035: switchgear, power transformers and shunt reactors, overhead lines, underground and submarine cables, reactive power compensation and HVDC converters. It finds three drivers landing in the same decade: the energy transition, the phase-out of SF6 gas under Regulation (EU) 2024/573, and the replacement of equipment installed in the 1980s and 1990s. As a result, planned additions peak in nearly every category between 2028 and 2032.

The headline numbers are large. TSOs plan around 34,000 km of new HVDC cable by 2035, more than 22,000 km of it underground and almost 12,000 km submarine, and 119 new bipolar converter stations against 38 today. They plan 2,820 new power transformers on top of a fleet of 5,649, and more than 64,000 km of high-temperature low-sag conductor alongside wider use of dynamic line rating to get more out of existing lines. STATCOMs above 150 MVA grow by 482 percent.

Switchgear shows the transition most clearly: 4,238 SF6-free gas-insulated bays are planned, but TSOs still expect to buy 10,819 SF6 air-insulated circuit breakers and 2,884 SF6 gas-insulated bays, so manufacturers will have to supply both technologies at once. Many TSOs name the availability of skilled workers as a main constraint.

The recommendations are split three ways: manufacturers should expand capacity and pass long-term demand down to their own suppliers, TSOs should harmonise technical requirements and plan jointly, and policymakers should aim industrial, permitting and skills measures where the report shows the biggest gaps.

ENTSO-E counts what Europe's TSOs need to 2035: 34,000 km of HVDC cable, 119 converters
ENTSO-E counts what Europe's TSOs need to 2035: 34,000 km of HVDC cable, 119 converters — Grid Brief

Why it matters

Grid plans fail on lead times as often as on money. A shared count of cables, converters and transformers turns many separate procurement plans into one order book that suppliers can build factories against.

Written by Victoria Shinder.