A 60 MW, 600 MWh liquid-air storage plant in Qinghai starts generating, with 10 hours of output
A 60 MW, 600 MWh liquid-air energy storage demonstration project in Golmud, in China's Qinghai province, was connected to the grid and began generating electricity on 30 October, pv magazine reports. It was developed by the state-owned China Green Development Investment Group with the Technical Institute of Physics and Chemistry of the Chinese Academy of Sciences, and the developer describes it as the largest grid-connected plant of its kind by both power and energy.
Construction began in July 2023. The plant is designed to deliver power continuously for 10 hours; CGDG says it can absorb about 600 MWh of surplus renewable electricity a day and supply an estimated 180 GWh a year. It uses ambient air as its working fluid and needs neither electrochemical cells nor underground caverns.
When charging, surplus electricity drives a three-stage centrifugal compressor that raises purified air to about 7 MPa; the heat of compression is kept as hot water at up to 195 C. The air is cooled in stages, liquefied at around minus 194 C and stored in insulated tanks near atmospheric pressure. To discharge, the liquid is pumped up to pressure, reheated and vaporised, and the expanding gas drives turbines, while the cold released during vaporisation is stored for the next charge. CGDG says all major equipment, including compressors, liquid expanders and cryogenic heat exchangers, was made domestically. The partners had earlier shown the technology at 100 kW.

What it means
Liquid air trades efficiency for geography: it needs no salt cavern or mountain reservoir, only tanks. A 10-hour plant at this scale is a reference point for long-duration storage where pumped hydro is impossible.