Mexico's CFE raises planned investment in 38 public-private renewable projects to $10.6 billion
Mexico's state electricity company, Comisión Federal de Electricidad (CFE), has lifted the planned investment in its mixed-investment renewable programme to $10.6 billion, pv magazine reported on 13 November. Director General Emilia Calleja Alor gave the figures in an appearance before the Chamber of Deputies.
The programme now counts 38 projects developed with private partners, with 8,026 MW of renewable generation and more than 2,500 MW of storage power. They are part of a wider CFE portfolio of 60 generation projects for 2024-2030 totalling 9,184 MW. CFE itself will build 22 of those, adding up to 1,158 MW, so the partnership projects account for roughly 87.4% of the planned capacity.
The model gives the state a 54% stake and the private partner 46%. The partner supplies the financing; CFE is majority shareholder and buyer of the electricity. Under the contracts CFE takes 70% of the output, and the remaining 30% can be sold on the market.
The numbers have moved in steps. The first selection, reported in June, covered 37 projects with 7,411 MW, of which about 6,710 MW was solar in 33 projects and about 700 MW wind in four, at an estimated $7.4 billion. In October CFE reported 8,025 MW and more than $10 billion. The latest update adds one megawatt and $0.6 billion but, according to pv magazine, CFE has not broken the change down by technology or project, nor given an updated solar figure.
The storage disclosure is equally thin. CFE stated more than 2,500 MW of storage power but not the energy capacity in megawatt-hours, the planned duration or how it is spread across projects.
Among the projects CFE will finance itself are further phases of the Puerto Peñasco solar plant in Sonora, where sections III and IV are to add 580 MW with commissioning in 2028, the Chicoasén II hydropower project in Chiapas and hydropower in Sinaloa. Calleja also announced a review of solar plants still waiting for grid connection and stressed that new generation must be coordinated with transmission, distribution and backup capacity.

Why it matters
The 70/30 offtake split is the structural point: CFE keeps most of the electricity and the market gets a minority, so the programme expands private capital without expanding private sales by the same amount. The missing storage hours matter for a grid where solar dominates the pipeline, because 2,500 MW for one hour and for four hours are very different assets.