Who carries the price risk: EPR2's dividends, NRG's $1,400/kW and New York's strike price
Several of today's items are, underneath, about who absorbs the difference when market prices do not cover the cost of an asset.
France's Cour des Comptes puts EPR2 at EUR 84 billion and says that below EUR 70/MWh EDF's financing needs rise sharply. Its answer to "who pays" is concrete: the contract for difference costs the state nothing until 2038 at the earliest, so in low-price scenarios the near-term option is for the state to forgo dividends - up to EUR 65 billion between 2026 and 2040.
New York's second bulk storage round answers the same question with an Index Storage Credit. NYISO's prices move too little for batteries to earn enough on spreads, so NYSERDA and the developer fix a strike price; profits above it go back, profits below it stay with the developer.
NRG's sale shows the other side: an operating Texas gas plant priced at about $1,400/kW by a buyer, while NRG says it builds new capacity for just above $1,000/kW. The buyer is taking on the plants' market exposure at that price.
Ember's cost model makes the financing assumption visible. At a uniform 7% cost of capital, 90% firm renewable supply in Africa comes out at $76/MWh; at regional rates it is $126/MWh.

Why it matters
The headline cost of an asset says little until the source states who carries the gap between that cost and the market price. In each of these cases the source says it - a state's dividends, a state storage credit, a buyer's balance sheet, a financing rate.