Who pays for growth: ENTSO-E's order book, Arizona's large loads and Brattle's DER case
Three pieces of news from early November look at load growth from three different angles, and together they show where the risk in grid planning now sits.
ENTSO-E's first transmission supply chain assessment is about quantity and timing. Europe's TSOs plan around 34,000 km of HVDC cable, 119 new converter stations against 38 today and 2,820 new transformers by 2035, with additions in almost every category peaking between 2028 and 2032 because the energy transition, the SF6 phase-out and the replacement of 1980s equipment all land at once (ENTSO-E). The report exists to give manufacturers a demand signal firm enough to build factories against.
In Arizona the question is who pays. Commissioner Lea Márquez Peterson told Utility Dive that customers now want proof that growth pays for growth, with large loads from data centres and semiconductor plants handled through supply agreements and upcoming rate cases (Utility Dive). Her concern is the cost breakdown behind decisions that increasingly happen outside full rate cases.
The Brattle report for Pew adds a third angle: what if the forecast is wrong. It estimates that removing barriers to distributed resources could avoid $614 billion of US system costs by 2050, and that if data-centre demand falls short, leaning on distributed capacity could cut overbuild costs between 2030 and 2040 by about 40 percent (Energy-Storage.news).

Reading them together
The three sources do not contradict each other; they describe different layers. Transmission backbones and HVDC links cannot be built in small pieces, so they need long commitments and shared demand signals. Large-load agreements decide who carries that commitment if a customer leaves. Distributed resources are the part of the system that can be added, or stopped, in small steps.
The common thread is lead time. Equipment that peaks in 2028 to 2032 has to be ordered now, against load that is still a forecast. The more of that forecast rests on a few very large customers, the more weight falls on the contract terms Arizona is asking about, and the more valuable capacity becomes that can follow demand rather than anticipate it.