The gap is dated, the fix is not: lead times decide this week's reliability reports
Three items this week read differently once the dates are put next to each other. NYISO's 2026 Reliability Needs Assessment puts the first statewide shortfall in 2033, about 225 MW, and the operator's own planning chief says the problem is time: new generation and transmission "take years to plan, permit, and build", so the needs "must be addressed today". The assessment also counts the bridge in days - emergency operating procedures on about 3.5 days next year and 21 by 2036.
The same week EDF bought the 250 MW, four-hour Holloway battery project in New South Wales. It is still at the environmental impact statement stage; the investment decision is targeted for late 2027 and operations from 2029. That is what "years" means in practice: a project bought this month becomes capacity in 2029.
FERC staff's winter assessment works on the shortest horizon of all. The capacity is there; the question is fuel. New England burned oil for about 40% of its generation in one hour on 25 January, and its distillate stocks were 46% below the five-year average in early October. In the West, the gain the report credits to wider markets comes from coordinating what already exists, not from new plant.

Why it matters
Each report names a quantity - megawatts, megawatt-hours, barrels - but the binding variable in all three is when it can arrive. A shortfall dated 2033 is already close when the remedy takes years to deliver.