Grid budgets rise faster than grids get built, from ACER's delays to DTE and Türkiye
Three pieces of news from this week describe the same imbalance from different places. ACER's 2026 infrastructure report says EU transmission investment almost tripled to 30.5 billion euros in 2025; DTE Energy in Michigan lifted its five-year plan to 44.2 billion dollars; and Türkiye's 2040 energy vision more than doubles installed capacity to 281 GW. In each case the money or the target is clear, and the constraint sits elsewhere.
In Europe the constraint is delivery. ACER finds that 22% of cross-border transmission projects of common and mutual interest are delayed each year, mainly by permitting, at a cost of around 4 billion euros of welfare per year of delay, while about 12.5 billion euros of congestion income has been set aside rather than spent on lines or tariffs. Household network costs have reached 84 euros per MWh, about 28% of an average bill.
DTE's plan puts 12 billion dollars into distribution and 23 billion into generation, and the utility argues that data-centre load from Google and Oracle will spread fixed costs and delay its next rate case. That works only if the load arrives as planned; the company also reported falling weather-normalised sales.
Türkiye's vision names its own constraint openly: 140 GWh of storage and interconnection rising from 5.4 GW to 15 GW are listed alongside the 175 GW of wind and solar, at a total cost of around 190 billion dollars.

What it means
The common thread is that capital is not the scarce input. Permits, connection capacity and the rules that decide who pays are, and those move slower than budgets. Customers pay for the gap either way, through congestion costs in Europe or through a larger rate base in Michigan.